# Production Launch Timeline — 2026-02-03

## Overview

During the [[wiki/meetings/2026-02-03-weekly-call-w-sebastian|2026-02-03 weekly sync]], Sebastian and Mark confirmed the Cordwainer website is nearly complete and on track for a production push in late the following week (week of 2026-02-09). The only remaining blocker is final page content from Eshock.

## Status at Time of Meeting

- Site build: **complete**
- Content: **mostly complete** — all major content received
- Remaining blocker: "About Us" pages and a minor contact page update, pending Eshock (Ben)

## Launch Timeline

| Step | Owner | Target |
|---|---|---|
| Ben (Eshock) finishes About Us pages | Ben / Eshock | End of week (2026-02-07) |
| Minor contact page update | Eshock | End of week (2026-02-07) |
| Production push | Mark + Sebastian | Late next week (~2026-02-13) |
| DNS cutover coordination call | Mark + Sebastian | Thursday 2026-02-12 |

## DNS & Launch Coordination

Mark noted the production push is procedurally straightforward but requires going through each step carefully. Sebastian planned to schedule a call for **Thursday, 2026-02-12** to walk through DNS and launch details together before the push.

> "It's not going to be complicated. It's just, you know, you got to do all the steps, step by step." — Mark Hope

## Action Items

- [ ] Sebastian to schedule launch coordination meeting with Mark for Thursday 2026-02-12 — include DNS steps on the agenda
- [ ] Ben (Eshock) to deliver completed About Us pages by end of week 2026-02-07