As of the January 8, 2026 sprint planning meeting, the Cora Italia website project is in a holding pattern, awaiting client-provided assets and content. The project was discussed briefly during the meeting between Melissa Cusumano and Karly Oykhman ahead of Karly's scheduled call with the client.
Blocked — Awaiting Client Assets
The team has not received the project assets or content needed to move forward. The last outbound communication from the team was on December 17, when Melissa sent the staging site link and a Google Doc outline to the client. No response or materials had been received as of the meeting date.
The agreed content process for this project is:
Melissa noted that the About page is the only page with fully written copy at this stage. All other pages have structural outlines with placeholder content indicating what each section should contain.
| Owner | Action |
|---|---|
| Karly | Confirm with client (Lincoln) that the outline-first / client-draft workflow is still the agreed approach |
| Karly | Follow up on outstanding assets and content during January 8 client call |
| Melissa | Write additional page copy by Friday if client content is not forthcoming |