wiki/clients/current/quarra/2026-03-09-content-blocker.md · 297 words · 2026-04-05

Content Blocker — Awaiting Client Delivery

Overview

As of the [1], all active Cora Italia projects are on hold pending content delivery from the client. No internal work can proceed until the client provides the required materials.

Status

Field Detail
Status Blocked — awaiting client
Identified 2026-03-09
Blocking All active Cora Italia projects
Owner Karly Oykhman

Details

During sprint planning, the team confirmed that every open Cora Italia deliverable is gated on content the client has not yet provided. Tasks were moved to an On Hold / Blocked status and due dates were removed to avoid false urgency in the sprint board.

At the time of the meeting, the team had received two or three new project briefs from Cora Italia but the underlying content assets (copy, images, or other materials) needed to execute those projects had not been delivered.

An English-Italian translation update was also noted as pending, though it was unclear whether that specific task had been completed.

Impact

Resolution Path

  1. Account manager (Karly) to follow up with Cora Italia contact to request outstanding content assets.
  2. Once content is received, tasks should be moved back to In Progress and due dates re-established.
  3. Notify the sprint lead (Melissa) so tasks can be re-prioritized in the active sprint.

Sources

  1. 2026 03 09 Sprint Planning|2026 03 09 Sprint Planning Meeting
  2. Index|Cora Italia Client Index
  3. 2026 03 09 Sprint Planning|Sprint Planning Meeting — 2026 03 09