Overview

Two long-overdue Didion design deliverables were flagged as urgent in the [1]. Both tasks have been sitting since approximately April 2nd (nearly two weeks) and must be completed by Friday, March 28 so that Sebastian can implement the meta ads and schedule a training session with Roy.

If the design team cannot deliver by Friday, Melissa will take over — but requires access to the original working files (currently only compressed JPEGs are available).


Deliverables

1. Didion Meta Ad Graphics

2. Didion Masa Narepa Sell Sheets


Key Decisions


Action Items

Owner Action Due
Design team (Łukasz/Mikhail) Deliver Didion meta ad graphics and Masa Narepa sell sheet revisions Fri 2026-03-28
Melissa Take over design tasks if files are shared and design team cannot complete Fri 2026-03-28
Sebastian Once graphics are ready, implement meta ads and schedule training session with Roy After graphics delivered

Downstream Dependency

Sebastian is blocked on Didion Meta Implementation until graphics are delivered. Once unblocked:

See also: [2]


Context from Stand-Up

"I wanted to have basically these metas done and up and running, because this again has been in here for a while… if they can't do it, they need to give me the access to the files, and I'll do them."
— Melissa Cusumano

"I have to wait for the graphic, which is why [I'm blocked]."
— Sebastian Gant

"If you're building them, it might be nice for Roy to watch you, because since he's been doing some of those trainings."
— Karly Oykhman